Waste at Oldhall’s Energy Recovery Irvine Facility

04/11/2026

At our recent meeting, guest speaker Scott Brown, delivered a presentation on 'Energy from Waste at Oldhall's Energy Recovery Facility at Irvine'.

Scott is the Facility's Project Director, and was accompanied and supported by his Project Manager, Alberto Andres.

On leaving school, Scott chose the apprenticeship route as a Civil Engineering Technician, gaining construction experience on waste industry projects over 5 years. Eventually moving onto studies at Paisley University achieving his Bachelors Degree in Civil Engineering. Then joining Scottish Power in charge of Asset Management of both Thermal Power stations and Renewable Energy Projects.

Having spent his early days in the design and disposal methods for waste projects, and experience in the thermal power industry, Scott found himself the perfect candidate to take the new emerging 'Energy from Waste' market forward in the UK.

The Oldhall Energy Recovery Facility is an energy-from-waste (EfW) plant located in the Oldhall West Industrial Estate in Irvine, North Ayrshire, Scotland which is developed by Doveyard Limited, a joint venture acquired by Octopus Renewables and operated by DY Oldhall Energy Recovery Limited. Alberto began by explaining the processing capacity handles approximately 180,000 to 185,600 tonnes per year of post-recycled, non-hazardous residual commercial and industrial waste that would otherwise go to landfill or export.

He added that the energy output generates roughly 17 MW to 19.3 MW of gross electricity providing power for over 30,000 homes, which exceeds Irvine's residential properties with potential heat options for local businesses.

The facility is regulated by the Scottish Environment Protection Agency (SEPA), featuring continuous emission monitoring (CEMS), indoor operations, ambient air and odour controls.

Scott interjected by explaining that the Scottish Government and SEPA have delayed the full enforcement of the biodegradable municipal waste (BMW) landfill ban until 2028. Following initial plans to ban biodegradable municipal waste to landfills starting 31 December 2025, the landfill ban enforcement has been delayed and pushed back to 2028 due to a shortage of domestic waste treatment and Energy-from-Waste (EfW) capacity.

Using a complex Process Flow Diagram, often used in chemical, industrial, and manufacturing engineering to map major mass and energy flows across a facility, Alberto explained in layman terms how the Oldhall site provides much-needed waste treatment capacity and will allow waste to be treated locally, rather than it being transported hundreds of miles away for disposal or treatment. All recyclable materials are removed before waste reaches the facility.

While backed for regional waste management capacity, the project has faced opposition from local groups like Irvine Without Incinerators and environmental organisations concerned with emissions and recycling incentives.

Following a lively question and answer session during which Scott responded with full and complete replies, Hugh Millar gave a worthy vote of thanks.

Alberto Andres, President Mary-Helen Shakespeare and Scott Brown
Alberto Andres, President Mary-Helen Shakespeare and Scott Brown